Feeds:
Posts
Comments

Posts Tagged ‘Infinite Bus’

Last week, my mentor mentioned that high-voltage power transmission circuits could sometimes be used to provide reactive power support when on potential but off load, particularly for parallel lines.  Anecdotally, based on my limited understanding of the Ferranti Effect, this seems perfectly reasonable: light loading on the line results in elevated line charging capacitance, which is then injected to the system at the point of connection.

Ferranti Effect

In order to understand the results, we have to understand the cause behind the Ferranti Effect.

All transmission lines (even the kind discussed in Radiation and Propagation courses) behave the same way once the line length approaches a tenth of the signal wavelength.  Due to the relatively low frequency of utility power (60Hz in North America and 50Hz in many other parts of the world), the wavelength is pretty long, so these effects only begin to appear in significantly long (greater than 300km) transmission lines.

The classical model is:

Source: Wikipedia

Lines of a moderate length (greater than 300km) can be modelled simply as a series resistance, series inductance and shunt capacitance – in Power Systems, we often call this model a “Pi section” (this moniker makes more sense if you separate the capacitance at the sending and receiving ends of the line, dividing them by two).  Longer lines (those exceeding 500km) are then an extension of an already-solved problem: they can simply be modelled using multiple moderate-length segments as appropriate.

Keen readers will notice that this is, quite simply, a two-port network model: we can consider each Pi section a black box, with sending-end voltage/current and receiving-end voltage/current.  Many of us rely on an approximation of how wires behave: in most applications, they have infinitesimal impedance, and so the impedance may be neglected in calculations.  However, when we approach power transmission, the voltages and currents are much higher than experienced elsewhere, which can have quite a profound impact on system operation.

I hope that this brief discussion provided a reasonable introduction or review.  If not, the Kathmandu University also has a very good handout on the subject.

Surge Impedance Loading

Based on the telegrapher’s equations and the above model, we can determine the characteristic impedance (also called surge impedance) of the transmission line as:

In all transmission lines, for power or signals alike, optimal power transfer occurs when the load impedance matches the characteristic impedance.  In Power Systems, we like to relate these quantities to units Power (Real, Reactive and Apparent) because these quantities can always be directly compared regardless of phase angles, power factors, harmonic distortion levels or voltage levels.

The Surge Impedance Loading converts the characteristic impedance (ohms) into a power (Watts) value:

If the amount of power being transmitted equals the SIL, the line mutual coupling (the inductance and capacitance in the model) cancels each other out, thus resulting in the line operating at unity power factor.  When the amount of power transferred is below the SIL, the power factor is leading (capacitive), and when the amount of power transferred is above the SIL, the power factor is lagging (inductive).

An intuitive model

Intuitively, I understand this behaviour by thinking about the cause of these impedances, though I am not a physicist, so this intuition is best understood as a useful analogy, not as fact.  I imagine lines have some slight twist when installed, giving rise to the series inductance.  Likewise, lines are conductors of different potential separated by a dielectric (air), which results in some capacitive coupling between lines.

Recall that power loss due to the resistance of a power line can be calculated using Joule’s law:

Similarly, the reactive power absorbed by (or injected from, if Q is negative) a power line into the system can be calculated using (where X is defined as negative for capacitors and positive for inductors):

The inductance is fixed, but the amount of reactive power absorbed by the series inductance is proportional to the current flowing across the line.  On a lightly loaded line, or where the receiving end is an open circuit, the current is very small, so the inductive nature of the line is minimized and the capacitive behaviour dominates.  Thus, the line is below the SIL and operates with a leading (capacitive) power factor.

Power transmission lines as capacitors

Finally, to get to the real point of this article. Given the above background, it follows that lightly loaded or open-ended lines will inject reactive power. With lightly loaded parallel redundant lines, it is therefore possible to open one line and use it to provide reactive power (var) support for the system.

For my simulation, I used two parallel 230kV lines, each 600km long, with three ideally-transposed phases on each right-of-way (in delta configuration with four bundled sub-conductors). These lines were supplied by an infinite bus (voltage source at 22kVrms line-to-line) with a 22/230kV Wye-Delta transformer. At the receiving end, a 300MW+5Mvar load was installed.

Here are the two circuits in steady state (note that BRK2 is open):

Dual 230kV Circuits, One Line Open

 

Note that TLine1 has a depressed receiving end voltage due to the current flowing a cross that line (the line inductance cancels out the Ferranti effect), but TLine2 has an elevated receiving end voltage due to the Ferranti Effect. Also note that the reactive power flow at the sending end for TLine2 is negative, indicating that reactive power is flowing “backwards” to the sending end.

Let’s take a closer look at what’s happening at the receiving end:

Mvar flow at receiving end of 230kV circuits

 

The breakers were configured to begin open and close in at 250ms to energize the circuit. Afterward, BRK1 remained closed and BRK2 was reopened at 500ms. We can see that reactive power initially flows across both lines, but when the receiving end circuit breaker is opened, reactive power ceases to flow. Note that the x-axis shows elapsed time of the simulation (in seconds).

The sending end, by contrast, is much more interesting:

Mvar flow at sending end of 230kV circuits

 

When both breakers are opened (until 250ms), there is a significant line charging capacitance drawing reactive power from the system. After the breakers close, the reactive power demand drops significantly (though it is still slightly capacitive due to both lines being lightly loaded). Once TLine2 is opened at the receiving end at 500ms, something interesting happens: the reactive power injected by that line into the system returns to its line-end-open state, while TLine1 increases its reactive power consumption in unison.

In conclusion, it is entirely possible to use a transmission line as a shunt capacitor.

Read Full Post »

My second “lab” for ECE4464: Power Systems II studied the effects of distributed generation (in particular, a large-scale wind turbine generation project) on the power system. Like ECE3333 (Power Systems I), this course is being taught by Prof. Rajiv Varma, Ph.D.

Using PowerWorld‘s Simulator software, we connected a large four-reactor nuclear generation plant (750MW per reactor, constant output) via two parallel transmission lines with a large city (modeled as an infinite bus). At the midline between the nuclear reactors and the large city, a transformer is installed at the midline bus to supply a different voltage to a nearby town. This town is near the proposed connection point of the Wind Turbine Generation (WTG) project; this project has a peak output of 85MW.

From the objectives:

In this lab, our objective is to study the potential impact of integration of distributed generation (in particular, a wind farm) using the PowerWorld Simulator software.  We simulate a very large capacity plant (a nuclear plant consisting of four reactors producing 750 MW each).  Because these reactors are large, they will provide some voltage regulation by supplying or consuming MVARs.

The nuclear plant serves a large city via two parallel transmission circuits, as well as the smaller city at the mid-line of one of these lines.  To simplify this lab, we model the large city as an infinite bus, which consumes any excess power generated by the plant.

In this manner, we can explore various phenomena resulting from distributed generation systems like wind farms, including the effects on power transfer and power system stability.  This lab provides insight on two very important issues in power systems, notably, the addition of distributed generation and the challenges involved with electrifying remote communities.

For my full report, see: Power Systems 4464 Lab 2 (PDF). Note that the small town bus has a constant 20Mvar reactive power demand, with a 40Mvar (nominal) shunt capacitor installed initially. Some modifications are made to the compensation scheme as part of the study and report.

Read Full Post »

Recently, I completed my first “lab” for ECE4464: Power Systems II. Like ECE3333 (Power Systems I), this course is being taught by one of the most inspiring professors I have ever had, Prof. Rajiv Varma, Ph.D.

Using PowerWorld‘s Simulator software, we repeated one of our basic labs from ECE3333 as an introduction to computerized modelling of power systems. We connected a single synchronous machine to an infinite bus across a 600km, 1000MW-SIL power line.

It is simplest for me to just lift the objectives from my lab report:

In this lab, our objective is to simulate a simple single machine infinite-bus configuration using the PowerWorld Simulator software.  We design a local generator system (a synchronous generator) having a nominal generation capacity of 500MW and with no predefined peak generation (that is, the generator is modelled as having infinite generation capability).

In this manner, we can explore various phenomena like power transfer, power system stability and the effect of shunt compensation on the midline.  We model a 600km span of transmission line with a shunt compensation device installed at the midline (300km from both ends) and determine the stability limit with and without this compensation device enabled.

Please see the following images, which show the simulation being run in PowerWorld:

500 MegaWatt generation, no compensation

500 MegaWatt generation, no compensation

500 MegaWatt generation with Synchronous Condenser Compensation

500 MegaWatt generation with Synchronous Condenser Compensation

For my full report, see: Power Systems 4464 Lab 1 (PDF). Note that the synchronous condenser installed at the midline is a Switched Shunt Compensation unit. I thought the standard inductor/capacitor schematic symbol looked a little boring, so I overlaid a synchronous condenser on top of it.

Read Full Post »